Factories Are Footing the Bill for the AI Boom's Power Hunger. The Answer Is to Build More Power Plants
From an Ohio brickyard to the PJM power market, factories are paying more as data centers soak up electricity. States are moving to make tech pay its own way, but the lasting answer is to build far more power.
Filed November 24, 2026 · 📍 OH 43215
Were you there? Share your story
Part of our continuing coverage: Don't Freeze America's AI Build-Out. Make Data Centers Pay Their Own Way, the Way Virginia Already Does
Key points
- An Ohio brickmaker's power costs rose about 90% in a year, largely from regional data center demand, Reuters reported.
- PJM's July auction hit its $325 price cap and still fell 6,831 MW short, with only 525 MW of new or upgraded generation clearing.
- Berkeley Lab estimates data centers could use 9.5% to 15% of U.S. electricity by 2030, up from about 4.5% now.
- Virginia is shifting grid costs onto data centers, Texas resumed permits, and tech firms signed a White House pledge to build or buy their own power.
In Sugarcreek, Ohio, the Belden Brick Company paid a fairly steady electric bill for years. Then last year its power costs jumped by about 90 percent, Reuters reported, driven largely by surging electricity demand from data centers going up across the region [1]. The brickmaker's monthly capacity charge alone rose from about $1,600 to $12,000. The company raised its brick prices 4 percent and still saw its profits shrink [1].
That is the less-told side of the artificial intelligence boom. Server campuses for chatbots and cloud computing draw on the same wires and power plants that manufacturers rely on, and on the grid that serves the mid-Atlantic and Midwest, factories are carrying a growing share of the cost [1]. For a nation that wants to bring manufacturing home, that problem must be solved quickly and fairly.
The Bill Lands on the Factory Floor
A Reuters review of federal energy data and interviews with manufacturers found industrial power costs climbing faster than costs for many households and other businesses [1]. By the news agency's own calculations from Energy Department figures, average industrial electricity prices rose 31 percent in Pennsylvania and 26 percent in Ohio in the year ending December 2025, against a 7 percent increase nationwide [1].
Belden Brick is not alone. Reuters reported that Plaskolite saw annual capacity charges at its plants in Ohio and Pennsylvania climb from roughly $200,000 to about $1.2 million, and that the company is weighing a direct natural gas supply of its own [1].
Why do factories feel this more sharply than families? Capacity charges, the fees that pay power plants to stand ready for the hottest and coldest days, make up roughly a tenth of a household bill but can be up to three times that share for a manufacturer [1]. And because utilities generally spread the cost of grid upgrades across all of their customers, regardless of which customer created the need, the expense of serving a new data center campus can end up on everyone's bill [1].
How a Grid Auction Became a Pocketbook Issue
The pressure point is PJM Interconnection, the grid operator for the mid-Atlantic and much of the Midwest [1]. PJM sets the capacity prices paid to generators based on its forecasts of supply and demand [1]. Those prices went from $28.92 per megawatt-day in 2024 to $329.17, an increase of more than 1,000 percent driven chiefly by data center growth, according to Reuters [1].
PJM's most recent auction, held in July for the 2028-2029 delivery year, settled at the federally approved price cap of $325 per megawatt-day, a shade below the prior year's cap of $333.44 [2]. The grid operator secured 138,318 megawatts of resources but still came up 6,831 megawatts short of its reliability requirement [2]. Its peak demand forecast for that year was about 2,000 megawatts above the one used in the previous auction, while only 525 megawatts of new generation and upgrades to existing plants cleared [2].
Demand is sprinting and new supply is walking. PJM has already taken emergency steps, including asking some customers to curb their use, to head off rolling blackouts as peak demand set a record, Reuters reported [1]. The price cap has kept results from climbing higher, but a cap does not build a single power plant.
How Big the Demand Really Is
A Department of Energy-backed analysis from Lawrence Berkeley National Laboratory, reported by E&E News in June, estimates that data centers now use roughly 4.5 percent of the nation's electricity and could account for 9.5 to 15 percent by 2030, with a central estimate near 11.8 percent [3]. That would more than double their share of the grid within a few years [3].
Individual projects are enormous. Reuters noted that the power needs of tech giants such as Meta and Amazon can be as much as 50 times those of even large manufacturers [1]. Yet manufacturers often share an electricity rate class with data centers, so they are being swept into state and federal proposals meant to shield homes and small businesses from data center-driven price spikes, and some of those proposals lump smaller factories in with the tech giants [1].
Belden and other manufacturers want Ohio regulators to take a harder look at how utilities estimate data center demand [1]. That is a fair request. If the forecasts are inflated, families and factories pay for capacity that is never used. If they are accurate, there is no time to waste in building.
States Move to Make Data Centers Pay Their Way
In Virginia, the State Corporation Commission in August ordered Dominion Energy to develop a tariff that assigns more transmission costs to data centers, siding with Gov. Abigail Spanberger's administration and with advocates who argued the facilities should pay for the energy infrastructure they require [5]. The utility was given 90 days to file a new policy covering so-called direct-connect equipment, such as substations and power lines built to serve large customers [5]. Spanberger said the order is expected to save Virginians hundreds of millions of dollars, though it remains unclear when regulators will rule on the new tariff or how much residential customers will save [5]. Dominion said it already has some of the strongest protections in the country to keep data center costs off household bills [5].
The principle Virginia is applying, that the customer who causes a cost should pay it, is sound and conservative, and it should be the rule in every state.
Texas took a different route. Gov. Greg Abbott ordered the Texas Commission on Environmental Quality in September to stop issuing environmental permits for data centers while the state grid operator, ERCOT, reviewed what the projects would mean for the power system [4]. The commission received word from the governor's office on Nov. 13 and resumed permit reviews on Nov. 16, ABC13 in Houston reported, even though ERCOT told the station its full findings will not be complete until Dec. 10 [4].
Washington's Pledge and the Case for Building
The Trump administration has pressed the technology industry directly. In March, President Trump and the chief executives of seven major tech companies signed a voluntary pledge at the White House under which the companies agreed to build or buy the electricity their data centers need, along with the infrastructure to connect that power to the grid [6]. To its credit, the industry put its name to the right principle. Because the pledge is voluntary, though, the follow-through will be tested in state rate cases and permit decisions.
Data centers are not the villain of this story. The country is far better off if the computing power of the coming decades is built in Ohio, Virginia and Texas rather than in China, and these projects can bring investment and a tax base to the towns that host them. The problem is that the grid has not grown fast enough to serve them and everyone else at once.
That points to the real answer. Rate design decides who pays, but only new power plants change how much power there is. The July auction cleared just 525 megawatts of new and upgraded generation against a shortfall of more than 6,800 megawatts [2]. America needs an all-of-the-above build-out: new natural gas plants, existing reliable plants kept on the grid, nuclear reactors restarted and new ones licensed, and faster approvals for the transmission lines that carry it all. When a tech company builds or buys its own supply, as the White House pledge contemplates, the grid gets bigger instead of more crowded [6]. And when a manufacturer like Plaskolite looks at securing its own gas supply, as Reuters reported, regulators should clear the way rather than stand in it [1].
What Comes Next
ERCOT's full review of pending Texas data center projects is due by Dec. 10 [4]. PJM's next capacity auction, for the 2029-2030 delivery year, is scheduled for December [2]. In Virginia, regulators still have to review Dominion's direct-connect policy and decide how much of the cost will shift to data centers [5]. In Ohio, manufacturers are pressing the state to examine the demand forecasts that help drive what they pay [1].
The goal is simple to state, if hard to reach: abundant, affordable, reliable power, with each big new customer paying its own way. Get that right, and the brickyard in Sugarcreek and the server campus down the road can both prosper. Get it wrong, and the families and factories of the heartland will pay the bill for an industry that can well afford its own.
Sources
- [1]Reuters (via The Detroit News)Big Tech data centers are driving up power bills at America's Rust Belt factoriesOpens in a new tab ↗
- [2]PJM Inside LinesPJM Capacity Auction Procures 138,318 MW of Generation Resources as Work Continues To Address Growing Electricity DemandOpens in a new tab ↗
- [3]Opens in a new tab ↗
- [4]ABC13 HoustonTexas Commission on Environmental Quality resumes data center permits before ordered review is completedOpens in a new tab ↗
- [5]Virginia MercurySCC orders Dominion to develop tariff to assign more transmission costs to data centersOpens in a new tab ↗
- [6]Opens in a new tab ↗
Should Congress speed up permits for pipelines and power plants?
- Yes, build more American energy
- Yes, but respect tribal and local input
- No, keep environmental reviews
Were you there?
If you were at the scene, or this story touched your life, tell us what you saw and what it was like.



Discussion 0
Sign in or create a free account to join the discussion.
No comments yet. Start the discussion.